Home : BusinessesNatural Gas : Pipeline Projects

Pipeline Projects

GAIL’s new pipelines – under implementation
(length and investment figures include spurlines)

Sr. No.

Pipeline

Length

Estimated Investment

1. Chainsa – Jhajjhar – Hissar pipeline 450 km. Rs. 1,250 crore

2.

Dadri – Bawana – Nangal pipeline 610 km. Rs. 2,200 crore

3.

Dabhol – Bengaluru pipeline 1,389 km. Rs. 4,543 crore

4.

Kochi – Kanjirkkod – Bengaluru – Mangalore pipeline 1,114 km. Rs. 3,032 crore

5.

Capacity Augmentation
Dahej – Vijaipur section
610 km. Rs. 5,000 crore

6.

Capacity Augmentation
Vijaipur – Dadri section
505 km. Rs. 5,500 crore

7.

Jagdishpur – Haldia pipeline 2,050 km. Rs. 7,600 crore

8.

Karanpur – Moradabad – Kashipur – Rudrapur pipeline 275 km. Rs. 250 crore
9. Capacity Augmentation
Bajera – Agra – Ferozabad section
70 km. Rs. 200 crore